Project Information
The Facilities
The Wawaitin, Sandy Falls and
Lower Sturgeon Generating Stations are small run-of the-river hydroelectric
facilities that have provided a clean and renewable source of power for over 90
years. All three facilities are now at the end of their designed service life.
These three generating stations operate at 25 cycles and therefore the power
cannot be used locally in Timmins and instead must be transmitted to Sudbury in
order to convert the power to 60 cycles and then be injected into the power
grid. Significant energy losses occur during the process of transmitting and
converting the 25 to 60 cycle power. All three plants are in need of structural
and electrical/mechanical repair in order to continue to provide Ontario with
this clean and renewable source of power.
Wawaitin Generating Station
The Wawaitin
Generating Station is a 10.4 megawatt facility located within the City of
Timmins municipal boundaries approximately 25 kilometers southwest of the urban
centre. The plant, placed in service in 1912, is accessed by a municipal road.
The Wawaitin Generating Station has a main dam at the northern end of
Kenogamissi Lake. The existing powerhouse is operated remotely. Plant operation
is controlled to ensure optimal energy production, while satisfying concerns of
Kenogamissi Lake cottagers regarding water levels and flooding concerns
downstream at Timmins. Typically, water levels are not allowed to fluctuate
more than 0.4 m in Kenogamissi Lake during the summer months, with sufficient
water passage through the Wawaitin Generating Station (GS) and/or spilling to
ensure adequate downstream supply to Timmins and the pulp and paper mill in
Smooth Rock Falls. Water level fluctuations must all be in compliance with the
Mattagami River System Water Management Plan.
The proposed Wawaitin GS
is planned to be located adjacent and to the north of the existing powerhouse.
The proposed Wawaitin GS will have two generating units with an approximate
capacity of 15 megawatts. Water in the existing intake canal would be conveyed
through the existing intake structure via a new steel penstock about 850 meters
in length to the new powerhouse and the adjacent substation. The proposed
facilities will be connected to the Hydro One Networks Inc. (Hydro One) Timmins
Transformer Station at 27.6 kilovolts to feed into the Timmins local
distribution system. This penstock system would be buried parallel and to the
north of the existing twin penstocks that feed the existing Wawaitin GS. Some
refurbishment to the existing dams will be required.
Sandy Falls Generating Station
The 3.0
megawatt Sandy Falls GS is located within the Timmins municipal boundaries
approximately 10 kilometers northwest of the urban centre. The plant, placed in
service in 1911, is well accessed by municipal roads. The Sandy Falls GS
receives water upstream of a 216 meters long spillway weir dam across the
Mattagami River. As a run-of-the-river plant, the Sandy Falls GS utilizes
available water only. Water levels in the headpond are not controlled by plant
operation, but are the result of natural water level fluctuations and/or
upstream controls and activities. Water levels are maintained to provide
sufficient water for Timmins by drawing down the upstream storages when inflows
drop in late summer.
The proposed Sandy Falls GS is located adjacent to
the east of the existing powerhouse and the new powerhouse will enclose one
generating unit with a nameplate capacity of approximately 5.5 megawatts. A
water canal will be used to convey water to the new powerhouse using the
existing intake structures No. 2 and No. 3. The intake structures and weir dam
will also need to be refurbished.
Lower Sturgeon Generating Station
The
5.3 megawatt Lower Sturgeon GS is located outside the municipal boundaries of
Timmins and approximately 48 kilometers north of the City. The plant, placed in
service in 1923, is accessed by a road west of Highway No. 655. The Lower
Surgeon GS has a dam, 165 meters in length, constructed in three differently
angled sections, extending across rock outcrops along almost the entire width
of the river.
The existing powerhouse is operated remotely. As a
run-of-the-river plant, there is no drawdown of the headpond. Any upstream
water level fluctuations are the result of natural water levels and/or upstream
controls or activities. In most years, sufficient water exists to operate the
plant at full-load on a continuous basis. OPG attempts to pass at least 15 m3/s
of water at all times for dilution of effluent discharge at the pulp and paper
mill at Smooth Rock Falls. In late winter, the forebay is drawn down to provide
water to Little Long GS downstream.
The proposed Lower Sturgeon GS is
planned to be located at the site of the existing powerhouse and will be
redeveloped to produce about 14 MW of power.
The Environmental Assessment
The redevelopment of the Wawaitin, Sandy Falls and Lower
Sturgeon facilities subject to the requirements of OPG's Class Environmental
Assessment for Modifications to Hydroelectric Facilities under the Ontario
Environmental Assessment Act (EA Act).
An environmental assessment was conducted to examine the
effects of the Project on the:
- Aquatic Environment (water, fish and other aquatic
life)
- Terrestrial Environment (adjacent trees, vegetation and
fauna)
- Socio-Economic Environment (local economy, local social
and economic uses)
- Archaeological and Built Heritage (archaeological,
building or structural resources.
- Atmospheric Environment (air and noise).
Some field work was carried out in 2005, however extensive
field work associated with assessing the effects of the Project was conducted
in 2006. The effects of the Project both during the construction and operations
phases have now been assessed and measures to mitigate, eliminate and reduce
negative effects as well as enhance positive effects were identified in the ER.
Field work indicated that the environmental impacts associated with the Project
would be temporary and minor and could be mitigated.
One (1) ER was prepared for all three (3) generating
stations.
Mattagami River System Water Management Plan
A Water Management Plan for the Mattagami River System
has been developed and includes eighteen waterpower structures and facilities
located along the river system that have influence on levels and flows. The
Plan was the result of a partnership between Ontario Power Generation, the
Ministry of Natural Resources and other private power producers which operate
facilities along the river as well First Nations and the general public, which
participated in the form of various advisory committees.
The Water
Management Plan was prepared in accordance with the Water Management Planning
Guidelines for Waterpower, as approved by the Minister of Natural Resources on
May 14, 2002. The Ontario Lakes and River Improvements Act requires
compliance by facility operators with the operating regimes (required flows)
established in the Water Management Plans and a compliance monitoring program
has been established.
June 2010- Notice of Minor Amendment Inspection
OPG, in consultation with the Ministry of Natural
Resources (MNR), is seeking a minor amendment on a temporary basis to the Water
Management Plan. This minor amendment will enable OPG to lower the approved
minimum upstream water elevation of Lower Sturgeon GS from 257.70m to 256.47m
from 1 July 2010 to 31 August 2010. The minor amendment is being sought to
enable maintenance work on the spillway of Lower Sturgeon GS. A Notice of Minor
Amendment Inspection providing details on the need for this temporary amendment
has been issued by OPG through local papers and this website. The Notice is
provided in the Notices/Decisions page.